Network Rail has completed major work to upgrade the signalling system and track at Bridlington.
Between Friday 22nd and Sunday 31st October, the 65-lever frame at Bridlington South signal box was upgraded to a modern control panel to improve reliability and reduce unplanned disruption for passengers.
Although the iconic levers were taken out of action, changes to the programme of work meant they were able to remain in place inside the signal box.
During the nine days, the new control panel was successfully installed and older mechanical signals next to the track were replaced with modern colour light ones. Work also took place to renew around 1.2km of track.
Train services resumed on Monday morning as planned.
Chris Gee, Operations Director for Network Rail’s North and East route, said:
“After the signal box and lever frame were listed just before this vital work started, we had to make some last-minute changes to the planned project. By relocating the new control panel within the signal box, we were able to bring a more modern, reliable railway for passengers, keep the much-loved equipment in place and make sure trains resumed on time.
“Buses have kept people moving between Driffield, Bridlington, Filey and Scarborough and I’d like to thank passengers, businesses and people in the community for their continued patience whilst this work was completed.”
The signalling system tells train drivers when it is safe to proceed and what route their train will take. It is essential for keeping trains a safe distance away from each other and for reducing delays.


Whitby And Scarborough Named Among UK's Top Christmas Holiday Spots For 2026
World-Class Cyclists to Race Through The East Riding For Tour Of Britain
Coastal Businesses Face Potential Impact As Preparations Begin For Tourism Tax
North Yorkshire Council Set to Spend £2.43m on New Winter Gritters
Historic Pullman Dining Coach Returns To Service After Decade-Long Restoration
Rescued Seal Pup Treated With Chilled Yorkshire Tea At Scarborough Sea Life Centre
Multimillion-Pound Cost Of New Scarborough Council Offices Revealed
Renewable Geothermal Heat to Warm Pickering and Kirby Misperton
Borehole Drilling to Begin Across Scarborough For Wastewater Upgrades
Green Light For Conversion Of Former Scarborough Army Centre Into Business Park
MP Calls for Better National Support Following RAF Fylingdales Wildfire Threat
Jail for Scarborough Drug Dealer







Comments
Add a comment